Thursday, December 6, 2007

The Outputs of Project Activity Definition

Taking the time to clearly define project activities reduces the chance for costly project delays. The process of defining project activities results in new or revised project documents or documentable items. These are the outputs of the activity definition phase of the project.

In any given project, there are three main outputs of activity definition: the activity list; supporting detail and WBS updates.
  • the activity list
    The first and most obvious output of activity definition is the activity list. The activity list results from using the WBS to decompose the project into a series of activities to be performed. To ensure completeness and adherence to project scope, the activity list should be developed and organized as an extension of the Work Breakdown Schedule (WBS).
  • supporting detail
    The second output of activity definition is supporting detail. Once an activity is defined, the next step is to clarify how it should be performed. To do this, you need to take into account project assumptions and constraints.

    Consider the example of Telecom Corporation's VPN project. The development of a new corporate web site is going on at the same time as the VPN project. The assumption that the web site development project uses standard technologies compatible with the VPN project must be documented in the supporting detail.

    The constraints imposed by the existing client infrastructure affect project activities and must be included in the supporting detail.
  • Work Breakdown Schedule (WBS) updates
    The third and final output of project activity definition are WBS updates. The WBS helps identify which activities to include in a project. If a missing deliverable is identified during the activity definition process, you must update the WBS to include that deliverable. You should also update the scope statement since it is a related document that includes a list of the project deliverables. Any changes in the deliverables must be reflected in the WBS and related documentation.
The outputs from activity definition include the activity list, supporting detail, and WBS updates. These outputs serve as important inputs to the next task required of a project management team—activity sequencing.

Wednesday, December 5, 2007

Project Decomposition and Templates

To complete any task, you need to know what tools are at your disposal. Project managers who are engaged in defining project activities use two main tools to accomplish this task: decomposition and templates.

Decomposition
Decomposition means breaking a project deliverable down into a list of achievable activities.

Telecom Corp. is a telecommunications company. One service that it provides to its clients is the virtual private network (VPN). VPN project deliverables include a firewall, routers, encryptors, Internet service, IP backbone, and secure remote access.

The last deliverable could be decomposed into the following three activities:
  1. provide remote access
  2. provide encryption key
  3. authenticate users
After dividing a deliverable into potential activities, the team must evaluate each activity using the following six criteria.
  1. Status is measurable.
  2. Sign of completion is visible.
  3. Start and end conditions are clearly defined.
  4. Time and cost are easily estimated.
  5. Duration has acceptable limits.
  6. Work assignments are independent.
The first criterion to consider is whether the activity's status is measurable. For example, one deliverable in a Telecom Corp. VPN project is secure remote access. One activity defined for this deliverable is authenticating users, and it is measurable. When half the users have working login IDs and passwords, the activity is fifty percent complete.
Whether there is a visible sign that the activity is complete is the second criterion. This sign could be the delivery of a document or product, or it could be the manager's signature. In the Telecom Corp. example, the visible sign that users have been authenticated to the network is when all users can access the network with a functional user password.

The third criterion to use is whether an activity has clearly defined start and end conditions. Once the beginning event has occurred, work may begin on the activity and continue to a visible sign of completion. For Telecom Corp., the authentication activity should only begin when the network is in place. The authentication activity is clearly finished only when the users are able to use their login IDs and passwords to access the VPN.

Whether activity time and cost can be easily estimated is the fourth criterion to consider. This is accomplished by estimating the time and cost of a project's activities. In the Telecom Corp. example of authenticating users to the VPN, time can be estimated at a few days.

The fifth criterion to examine is whether an activity's duration is within acceptable limits. Although there is no set rule on this, projects should avoid activities with long durations. Delays in such activities can create serious scheduling problems. In evaluating Telecom Corp.'s authentication activity, duration can be estimated at a few days. Delays here would not create huge project delays or large-scale scheduling problems. The authentication activity then meets this fifth criterion.

The final criterion is an activity's level of independence from other project activities. Independence in an activity means that once work has begun on the activity, it may continue without interruption. For example, once Telecom Corp.'s authentication activity begins, it is not dependent upon any other project activities for completion.

Templates
The second tool a project manager and team uses to define project activities is a template. A partial or total activity list, or WBS from a previous project, can be used as a template for a current project. Using templates simplifies project activity definition and reduces project costs by improving team efficiency.

To define project activities, project managers use decomposition and templates. Decomposition means breaking project deliverables into achievable activities. A template is a partial or total WBS, or activity list defined in a previous project, which can be used in a current project.

Monday, December 3, 2007

The Inputs to Project Activity Definition

When a project reaches the activity definition phase, certain documents or documentable items have already been established. These "inputs to activity definition" include the Work Breakdown Schedule (WBS), scope statement, historical informaiton, constraints, assumptions, and expert judgment.
  • Work Breakdown Schedule (WBS)
    One of the principle inputs to activity definition is the WBS. This document defines project tasks and deliverables.
  • scope statement
    The scope statement refers directly to project justification, project objectives, project deliverables, and project product description.
  • historical information
    Historical information is another important input to activity definition. Consider activities required on previous, similar projects in defining current project activities. After all, if something works, why not repeat it?
  • constraints
    Constraints are also an input to project activity definition. A constraint is anything that can limit the project management team's options.
  • assumptions
    Assumptions are the fourth input to activity definition. For planning purposes, assumptions are factors that are considered to be true. Over the course of the project, these factors may turn out to be true or false.

    Assumptions always carry a degree of risk. For example, if assumptions about materials or costs are false, a project may be delayed or exceed its budget.
  • expert judgment
    The final input to activity definition is expert judgment. Expert judgment is advice from people with specialized knowledge or training that directly relates to your project. Some sources of expert judgment are:
experienced employees in the organization
outside consultants
professional associations
industry watch groups.
The inputs to activity definition are an important part of any project. These documents and documentable items help the project manager and team to determine project deliverables and the tools and techniques needed to achieve the deliverables.