Three Ways to Diagram Projects

Before leaving on a trip you gas up the car and then check the road map for the best route. Project managers also have road maps that they can follow to choose the best route for their projects.

The project network diagram, also known as a project manager's road map, is one of the inputs to schedule development. It is a schematic display of the project's activities and their logical relationships or dependencies. It may be produced manually or on a computer, and may include full project details, or have one or more summary activities. The diagram should be accompanied by a summary narrative that describes the sequencing approach.

Project managers use three principal types of network diagrams: precedence diagramming method (PDM), arrow diagramming method (ADM), and conditional diagramming method (CDM).

Precedence diagramming method (PDM)
The precedence diagramming method (PDM) uses nodes to represent activities. Arrows join the nodes together and indicate the dependencies between activities. This technique is also known as activity-on-node (AON) and is the method most widely used by project management software.

The precedence diagramming method is based on four types of dependencies: finsh-to-start, finish-to-finish, start-to-start, and start-to-finish. The first activity in a dependency relationship is referred to as the "from" activity. The second is referred to as the "to" activity.
  • In a finish-to-start dependency the "from" activity must finish before the "to" activity can start. For example, on a courseware development project, you must finish the scripting before the graphics can be developed.
  • In a finish-to-finish dependency, the "from" activity must finish before the "to" activity can finish. For example, car body and engine production can be started at the same time. The last step in the engine production phase is to install it in the body. Therefore, the body must be finished before the engine can be finished.
  • In a start-to-start dependency, the "from" activity must start before the "to" activity can start. For example, on a telemarketing project the compilation of phone lists must be started before people can actually be called.
  • Finally, in a start-to-finish dependency, the "from" activity must start before the "to" activity can finish. For example, if your car refuses to start, you may need to jump start the battery with booster cables. The engine must start before you can finish jump starting the car.
In the precedence diagramming method, finish-to-start is the most commonly used type of dependency.

Arrow diagramming method (ADM)
The arrow diagramming method (ADM) uses arrows to represent the activities and connects them at nodes to show dependencies. This technique is also known as activity-on-arrow (AOA). Although less common than the PDM, it is still the technique of choice in some application areas.

In an ADM, "dummy activities" are used to show logical relationships when logical relationships cannot be completely or correctly described with regular activity arrows. A dummy activity uses no resources, has a duration of zero, and is represented by a dashed arrow.

Conditional diagramming method (CDM)
The conditional diagramming method (CDM) allows you to diagram activities that must be repeated more than once. This technique also allows you to diagram non-sequential activities. The two most widely used techniques for creating a CDM are graphical evaluation review technique (GERT) and system dynamics.

Activities that must be repeated more than once are known as loops and can affect the project schedule if their durations are not calculated properly. An example of a loop may be the testing component of a project that needs to be repeated more than once.

When your project has an activity that only occurs under the right conditions, you will need to add conditional branches to the schedule. For example, a conditional branch may be added following an inspection activity. This would indicate that if errors are detected in the product, changes to the product's design may be needed.

Project managers use standardized network diagrams to create project network diagrams faster than they could by drawing them out using a pen and paper. These networks can include an entire project or only a portion of it. Portions of a network are commonly referred to as subnets or fragnets. Subnets are especially useful when a project has several identical or near identical features. Examples of subnets include constructing floors in a high-rise office building, or doing clinical trials on a pharmaceutical project.

Project network diagrams can be used as a guide for your project team and to help your management team better monitor project progress. This ultimately increases your chances of executing a successful project.

5 comments:

kvansh said...

Well Written and explained.

Anonymous said...

graphical examples please...

Anonymous said...

The Documentation Specialist (DS) is responsible for creating User Guides, Administrator Guides and other training materials. In our experience, programmers do not always have the written communication skills to write documentation in a way that a laymen can interpret it, that is why it is important to have a separate resource for this function.

Anonymous said...

If you would like to use these posters to morally discourage use of fake software, Project Management Software
you can download the original Adobe InDesign package or PDF files.

Anonymous said...


Tag: PM206A57. Let me share all of you about #5 Tips for Project Management Success,, I hope you enjoy it

1. Plan your day using time management techniques

As a project manager, time management skills are essential because you are dealing with a wide range of tasks that demand a quick turnaround time. Planning your day will go a long way in keeping you organized and increasing your productivity. Assist your task planning by using project management software which helps you track the work of you and your team.

If you are not very tech savvy, a simple to-do list can also be a great organizational tool. Prioritize your most important tasks by putting them at the top of the list and less important ones at the bottom. Having a visual plan of your daily tasks helps to keep you on track and aware of time.

Related post: Free ebook 104 secrets to become a great project manager

2. Include stakeholders in important project conversations

While you will have plenty of responsibilities regarding the project, don’t neglect your clients.

Good communication is essential is keeping both parties informed of project progression, curtailing scope creep, and apprised of changing requirements. Some clients may have different expectations when it comes to communication, so make sure to establish the frequency and type of communication (like emails, phone calls, and face-to-face conversations) at the beginning of your project.

Establishing communication expectations early helps alleviate stakeholder uncertainty about communication frequency and delivery.

3. Regularly communicate with your team

Daily team communication helps keep misunderstandings and unclear requirements under control. Keeping your team informed in every step of the project is essential to project management success.

For example, a study published by Procedia Technology found that good communication skills were the cornerstone of project management. The study examined over 300 “construction project managers, architects, construction managers, engineers and quantity surveyors” and their successes and failures on various construction projects.

4. Anticipate project setbacks

Even the best-laid plans often go awry.

Remember that even with a high amount of planning and attention to detail, your project may still encounter some challenges. Pay attention to complaints from stakeholders or colleagues, and other warning signs, like a missed deadline or cost overrun, that there may be a problem.

Preventing a crisis will keep your project running smoothly, save you a lot of time, and keep you, your team, and your stakeholders confident in progressing with the project.

Unfortunately not every complication can be avoided. Crisis management skills are essential for dealing with the unexpected. Project managers need to be flexible and pragmatic. Improvise and make sharp decisions when needed.

Related post: 92 free project management templates

5. Stay focused on the details

A common problem project managers encounter is having the project aims not aligned with the organization’s objectives. A great project manager will strategize a plan for the project to lead back to the overall success of the business.

Know your project’s scope by heart and avoid wandering outside of the project’s requirements. It’s too easy to get lost in minor details and forget what your focus is, so a well-planned project scope is essential for success.

And final, you should use KPI to measure effectiveness of the project, here are full list: 76 project management KPIs