To verify that your WBS is complete, you need to ensure that the lowest-level work packages can be appropriately scheduled, were appropriately budgeted, and can be appropriately measured. Keep in mind that the work packages, which also are referred to as tasks, are the constituent components of activities, which in turn are the constituent components of project deliverables.
1. You must ensure that work packages can be appropriately scheduled.
Duration estimates were crucial in creating the WBS, but to verify that the WBS is complete, you must be able to appropriately schedule each low-level work package. This means that each work package must have a clearly defined starting and ending event.
The starting event can be the result of completing another phase or activity, but the ending event should complete the work package. If the ending event leads to another activity, the new activity should be decomposed to create an even lower level within the WBS.
In general, you should schedule the lowest-level work packages for less than three calendar weeks, or 15 business days. This avoids long duration activities whose delay could create serious scheduling problems. If the work packages in your project are longer than three weeks or you can separate tasks within the activities with distinct durations, try to decompose them further.
2. You must ensure that work packages were appropriately budgeted.
The second criterion for verifying that a WBS is complete is whether or not the lowest-level work packages were appropriately budgeted. To determine this, project managers must look at the cost estimated for each low-level work package and compare it to what they would expect it to cost based on their previous project experience.
For the WBS to be properly decomposed, the amount estimated for each work package must fall within a specified range of the expected amount.
3. You must ensure that work packages can be appropriately measured.
Measurability is the third criterion for verifying that your WBS is complete. For any lower-level work package in the WBS, there must be a sign of completion. A sign of completion is any visible indication that a work package is finished. For example, a sign of completion could be:
- an approving manager's signature
- the delivery of a physical product or document
- an authorization to proceed to the next activity.
For example, if team members can report a percent complete on an activity to a specific person, department, or team, the activity is measurable. Examples of measurable and nonmeasurable activities are provided below.
- Nonmeasurable. "Communicate progress to others" is a nonmeasurable activity. This task has no sign of completion, so it will simply stop at the end of the project. It is not possible to estimate the progress of the task, since it has no distinct parameters.
- Measurable. If the task "communicate progress to others" were broken down to "report weekly progress on phase one to executives," the task would be measurable. It would be possible to report what had been accomplished in the reporting period.
The WBS is important for defining project scope because it defines all the work in the project. Since project teams frequently refer to the WBS throughout the project, finalizing the WBS and verifying its completeness is the key to project success.
2 comments:
Hi!!
This blog gave good information IT project Management with vivid explanation PRIMAVERA TRAINING is the best option to the carrier in cistotech in Hyderabad.
Appreciate Your Work... Thanks for Sharing Useful Information. I Just want to Share Some information related to Primavera training in chennai hope it is useful for the Community Here.
Post a Comment